The first installation of the segmental girder box (SGB) at Light Rail Transit (LRT), Jalan Boulevard Utara, Kelapa Gading Timur, North Jakarta begins.

Launching gantry system is not using a crane car

PT Jakarta Propertindo (Jakpro) President Director, Satya Heragandhi said, until the end of this year, 1,300 SGBs are targeted to be installed at LRT lane as long as six kilometers, starting from Kelapa Gading Depot until Velodrome Rawamangan Station.

As the initial stage, he stated, 4 SGBs will be installed using launching gantry system.

LRT Construction Phase 1 Reaches 12.75 Percent

"Launching gantry system is not using a crane car. Once pulled up, it is directly assembled by the launcher," he expressed, Monday (5/29).

To speed up its installation, his side intends to prepare four units of launching gantry. Thus the project can be completed this year, and then continued with railway construction and train procurement in 2018.

"The pile is big enough and can withstand earthquakes with a magnitude of 5.2 on the Richter scale. Thus far the project has touched 21 percent," he closed.

Linked News
Popular News indeks
  1. Water Channel on Jalan SPG 7 Being Improved

    access_time18-09-2026 remove_red_eye683 personNurito
  2. Jakarta Govt Fully Backs Kanye West's Ye Live in Jakarta 2026

    access_time16-09-2026 remove_red_eye470 personDessy Suciati
  3. No Damage Reported Following Magnitude 5.9 Seribu Islands Quake

    access_time12-09-2026 remove_red_eye462 personBudhi Firmansyah Surapati
  4. Pramono Endorses Five-City Tour for Jazz Goes to Campus

    access_time12-09-2026 remove_red_eye461 personDessy Suciati
  5. 5M Movement Promoted to Create an Organized Utility Network

    access_time18-09-2026 remove_red_eye345 personFakhrizal Fakhri